Construction Labor Cost Calculator
Estimate how many days a job takes and what the labor costs, from the work area, output per worker and daily wage.
How it's calculated
Days = work area ÷ (output per worker per day × workers), rounded up. Cost = days × workers × daily wage.
Each measurement has its own unit menu, so you can enter whatever your plans use. Results are shown in several units at once.
Worked example
With work area 200 m², output per worker per day 8 m², number of workers 4, daily wage per worker 60, the calculator gives: days needed 7 days; worker-days 28; labor cost $ 1,680.00; labor cost per square metre $ 8.40; labor cost per square foot $ 0.78.
Good to know
Output varies with the task, site access and weather. Use figures from your own past jobs where you have them, and keep a margin for rain days.
Frequently asked
What is a typical output for bricklaying?
Skilled bricklayers often lay several hundred bricks a day, which is around 5 to 10 m² of half-brick wall, but this varies a lot.
Does this include supervision?
No. Add supervision and overhead separately.