Excavation Volume Calculator
Work out how much soil an excavation removes, how much it swells when dug, and how many truck loads to haul it.
How it's calculated
Bank volume = length × width × depth. Soil takes up more space once dug, so loose volume = bank volume × (1 + swell), and trucks are filled by loose volume.
Each measurement has its own unit menu, so you can enter whatever your plans use. Results are shown in several units at once.
Worked example
With length 10 m, width 6 m, depth 1.5 m, soil swell when dug 25 %, truck capacity 8 m³, the calculator gives: volume in the ground (bank) 90 m³; loose volume after digging 112.5 m³; truck loads 15 loads.
Good to know
Typical swell is 10 to 20 percent for sand, 20 to 30 percent for common soil and 30 to 50 percent for rock. A sloped excavation needs a separate calculation.
Frequently asked
What is the difference between bank and loose volume?
Bank volume is soil in place. Loose volume is the same soil after digging, when air gaps make it bulkier.
Does this handle sloped sides?
No. For battered sides, split the pit into sections or use the average of top and bottom areas.